XAT 2020Quantitative AbilityTime and WorkHARD+1 / −0.25

X, Y, and Z are three software experts, who work on upgrading the software in a number of identical systems. X takes a day off after every 3 days of work, Y takes a day off after every 4 days of work and Z takes a day off after every 5 days of work.
Starting afresh after a common day off,
i) X and Y working together can complete one new upgrade job in 6 days
ii) Z and X working together can complete two new upgrade jobs in 8 days
iii) Y and Z working together can complete three new upgrade jobs in 12 days.

If X, Y and Z together start afresh on a new upgrade job (after a common day off), exactly how many days will be required to complete this job?

Select an option to reveal the answer and explanation

Practice the full paper

Attempt XAT 2020 Question Paper with real exam interface and instant grading.

View Paper →
CatMate

CAT & XAT prep made focused.

Build exam-ready momentum with realistic mocks, safe auto-save, and analytics that surface exactly what to fix next.

Practice

  • CAT Sectional Tests
  • XAT Sectional Tests
  • CAT Previous Year Papers
  • XAT Previous Year Papers

Prepare

  • XAT Preparation
  • Analytics
  • Profile
  • About

Legal

  • Privacy Policy
  • Terms of Use
© 2026 CatMate. All rights reserved.
Made in India